Case Reference
Hotel Fit Fun

Hotels, Swimming pools and wellness centres | Liberec

Installed micro power plant:
TEDOM CENTO T200 - 200kWe

Total annual saving:
321 000 CZK

Annual savings per room: 1.933 CZK

  • 166 rooms
  • extensive wellness center
  • 2 restaurants and caf and cafes
  • bowling center

Heating system: In-house gas boiler room. Electricity: Building connected to the high voltage network.

ABOUT THE CLIENT

This hotel with 166 rooms is one of the largest hotels in the Krkonoše mountains. All of the rooms are three-star quality and are located in the two wings of the hotel. Both wings are connected by a glass corridor. The large Wellness & Balneo Centre includes a swimming pool, sauna, fitness centre, 2 massage rooms, two large hot tubs, an infrared sauna and tanning room.

ONSITE POWER MICRO POWER PLANT

Installation of a cogeneration unit with heat output of 253 kW covers most of the hotel’s heat requirements. The gas boiler, as a bivalent source, is only used to provide additional heating during the winter months. Cogeneration covers heating requirements not only for heating of the hotel, but also for heating the swimming pool and heating hot water for wellness and other services which the hotel provides. During the winter months, it covers more than 90% of electricity consumption, thus significantly reducing payments for renewable sources of electricity.

Production data

Consumption OnSite produces KGJ Coverage of consumption
Electricity 996 MWh 589 MWh 59 %
Heating 1591 MWh 1269 MWh 80 %