Case Reference
ÚVP Běchovice, Prague
Installed micro power plant:
2× TEDOM MICRO T30 - 60 kWe
Total annual saving:
144 000 CZK
- office and production facilities
- hostel 50 rooms
- car service
Heating system: In-house gas boiler room 730 kW Electricity: Building connected to the low voltage network.
ABOUT THE CLIENT
The ÚVP Běchovice complex in Prague 9 – Běchovice offers leases for non-residential space (offices, storage space, workshops and parking areas) and virtual office services (provision of a registered office or contact address, receipt and forwarding of post and short-term lease of meeting rooms). The hostel, which is designed as a separate operation offers accommodation services.
ONSITE POWER MICRO POWER PLANT
A micro power plant was installed as an additional source to complement the existing gas boiler room with an output of 630 kW and additional boiler room for the hostel with 92 kW. The cogeneration units of the micro power plant serve as the primary source of heat. Only when their output is not sufficient to meet the requirements for heating does the main boiler room also switch on.
Production data
Consumption | OnSite produces KGJ | Coverage of consumption | |
---|---|---|---|
Electricity | 151 MWh | 32 MWh | 21 % |
Heating | 570 MWh | 463 MWh | 81 % |